With the help of various actions and energy management evaluations, new measures for increasing energy efficiency at the university are ongoing. Some major measures are described in more detail below.
Energy savings at the THM due to the nationwide gas shortage
From September 2022, measures for saving energy in public buildings were decided by federal ordinance. In addition, the State of Hesse has issued a catalogue of measures with the target of saving 15% in heat energy and 5% in electricity consumption compared to the previous year. By limiting the air temperature in rooms to 19°C, introducing minimal heating of stairwells and corridors as well as lowering the heating circuit temperature at weekends and reducing the outdoor lighting on the campus, the THM has largely achieved the set goals. The 1,330 MWh of heat saved could heat around 60 single-family homes. Compared to December of the previous year, 4.5% energy was saved.

en:key and hydronic balancing in Friedberg
In order to increase energy efficiency and user comfort, a hydraulic balance was carried out on the A and B campuses in 2022 and an individual room control system was installed. To do this, the valves on almost 1,000 radiators were replaced and the system hydraulically balanced. In the process, around 800 en:key valve controllers and a total of 345 wall control units were installed in the rooms in place of the normal thermostatic heads. The respective room sensor records the presence of the occupants and uses this to create an individual usage profile. With this profile, the room temperature is raised by a servomotor on the valve when the room is in use and lowered again at other times. In addition to better user comfort, heating energy costs can be reduced significantly.
Based on the experience gained from projects that have already been implemented, a saving of at least 10% is expected.
A12 refrigeration system
IT-S operates a server room in building A12. The temperature is kept low by means of air cooling units. The waste heat is supplied to a cold water network. The coldness was previously maintained by two compact chillers. Ever since the two devices were commissioned, there have been repeated problems with the system hydraulics and cooling supply, especially when outside temperatures are high. As an optimisation measure, the two old devices were replaced with a new refrigeration system with higher efficiency. The system can work in so-called "free cooling mode" at high outside temperatures. Here no extra work is required to operate the refrigerant compressor. The heat is dissipated exclusively via the two enlarged dry coolers on the roof. The new system, which is built with 100% redundancy in refrigeration, has significantly increased operational reliability.
Operation optimisation and noise reduction in the LTZ
In 2022, the air volume flows in buildings D13, D14 and D15 were adjusted with considerable energy and noise reduction. The evaluations so far show energy savings of up to 40% compared to the same month last year, particularly in terms of heat. The electricity consumption of the ventilation system was also noticeably reduced.
Optimization and heat distribution on the C campus
The conversion and renovation of a district heating distribution network was planned and successfully implemented on the C-Campus in Giessen in 2020 and 2021.

LED lighting building A21
In the A21 building, the lighting was replaced by modern LED lighting. This is not always as simple as expected. An exchange of the lamp, i.e. only the replacement of the existing tube with, for example, an LED tube would lead to the approval of the entire lamp. The LED lamps are significantly heavier than classic tubes. The only solution is therefore the exchange of the entire lamp. This was partially implemented by retrofit lamps, so that the plastering and string work was limited, but for optical reasons, ceiling slabs had to be replaced if the new lamps were smaller than the new ones. We think the effort was worth it! This project was also funded from the ICSP.
Operation optimisation in building D16
In 2021, the control technology in building D16 was further optimised. Previously, the rooms were heated up to 20°C and then cooled down from 20.5°C. The so-called "dead band" was increased from 0.5 to 2.0 Kelvin in the course of the optimisation measure.

By changing the sequences, an energy saving of 14% could be achieved in Building D16 in the last heating period compared to the previous year.
Facade renovation of Building A5
In building A5 on the Friedberg campus there are mostly laboratory rooms from Department E Maschinenbau, Mathematics, Natural Sciences and Data Processing as well as business. Due to the year of construction, there were high heat losses through the facade.
The steel girders and the Reglit glazing did not offer good thermal insulation, so that an extensive renovation took place here in 2019. Instead of the previous glazing, insulated aluminum sandwich elements now adorn the façade and ensure noticeable energy savings and better user comfort. The windows and sectional doors were also modernized in terms of energy and the latter were also enlarged in the process.

Facade renovation of Building A7
The facade of Building A7 on the Friedberg campus was renovated in 2020. For this purpose, the semi-transparent components and windows were replaced. The insulated aluminum sandwich elements of the new facade reduce the heat loss of the building and at the same time ensure better user comfort.
Plant optimisation in D11
Building D11 with a floor space of 1,085 m² was completed in 2007. The energy consumption was particularly high in 2016 due to the biochemistry laboratories with a consumption of 485 kWh/m² electricity and 593 kWh/m² heat. After intensive analysis, the deficiencies in the existing technology structure were removed.
In order to ensure regular operation, the MSR technology together with the system software was replaced. This not only provided transparent system operation and the implementation of new control functions, but also increased operational reliability at the same time.
Further measures to improve the existing technology were:
- Adaptation of the laboratory running times through the use of room control units (laboratory and maintenance operation)
- Adjustment of the air volume flows of the fume hoods (laboratory and maintenance operation)
The implementation of the measures resulted in savings of 330,000 kWh warmth and 150,000 kWh electricity per year with an amortization period of approx. 1.6 years.
Pilot project for energetic refurbishment of building A10
The implementation of measures to save energy in existing buildings is on the one hand versatile and complex, but on the other hand it is also characterized by a high degree of effectiveness and efficiency with at the same time - under certain boundary conditions - relatively low financial investment.
To determine where energy-saving measures can be implemented most effectively, the energy consumption of the first buildings was systematically analyzed and compared with the area-specific consumption. For the Giessen campus, it was determined that building A10 has both the highest total energy consumption and a very high area-related energy consumption. The precise energy flows and usage of this building were then analyzed. It is characterized by highly heterogeneous usage (physics and chemistry laboratories, lecture halls, cafeteria, pastry shop, offices, etc.) and the resulting diverse requirements for its technical systems.
To significantly increase energy efficiency, measures were identified that are characterized by low expenditure of time and investment costs as well as the shortest possible amortization period. The following individual measures have been implemented:
- Installation of an individual room control based on enOcean technology
- Insulation of the heating lines in the building
- Retrofitting of energy meters
- Adjustment of the running times of the ventilation in the canteen
- Adapt the heating curve of the control circuits
- Conversion of the lighting to LED technology
- Installing CO2-Traffic lights and user training
- Renewal of building automation
The pilot project was funded by the State of Hesse ("Integrated Climate Protection Plan 2025 Innovation and Structural Development Budget") with €83,000.
Operation optimization building B21
In the course of the project "Development of an energy concept for a CO2-neutral university" - ECO2 for short - an operational analysis and optimization of the ventilation system in the rented Roxy Cinema in Giessen was carried out.
The aim was to check the function of the digital building automation newly installed in autumn 2016 and to determine suitable optimized operating parameters. This should enable increased user comfort with reduced energy requirements. The new parameters were based on measurements of room temperature and CO 2-Concentration during lectures. These were also carried out and evaluated by students of the "Building Systems Engineering" course as part of a project work.
The system parameters have already been adjusted based on the new findings. Particularly positive: The changes in the room climate have been well received by the users.
With the new control and the changed operating parameters, around 25% of primary energy is saved. This corresponds to a reduction in CO 2-emissions of about 9 tons per year.

